Folsom Lake Crossing Schedule
| Design complete | September 2006 |
| Environmental Record of Decision | October 2006 |
| Project Cooperation Agreement | November 2006 |
| Construction Proposals Received | December 2006 |
| Groundbreaking Ceremony | February 2007 |
| Construction Began | March 2007 |
| Bridge Open to Traffic | March 28, 2009 |
Folsom Lake Crossing Costs
The total cost of Folsom's new bridge below the dam is about $132 million, including pre-construction, planning, engineering and real estate costs. The U.S. Army Corps of Engineers will pay approximately two-thirds of the cost. The City of Folsom's share is approximately $32 million, most of which is being provided from Sacramento County transportation sales tax Measure A funds. The Sacramento Area Flood Control Agency and the state Department of Water Resources are adding about $10 million.

October 2008