1. Historic District Utilities Rehab Project
2. Sewer System Scada Improvements - Various Locations
3. Installation of Water System Sampling Stations - Various Locations
4.
Water Service Replacement - Various Locations
5. Water Meter Installation Project
6. Nimbus Tank Rehabilitation Project


1. TITLE - Historic District Utilities Rehab Project
DESCRIPTION - Replacement of sewer & water systems
LOCATION - In the area of School, Bridge, Scott, Sutter, Coloma, Leidesdorff
PROJECT MANAGER -
Marcus Yasutake
CONTRACTOR: Syblon Reid
CONSULTANT: Peterson, Brustad, Inc.
START DATE: November, 2008
ESTIMATED COMPLETION DATE - June, 2009
Project Cost - $1,370,000
% Complete - 85%
2. Title: Sewer System SCADA Improvements
Description: Installation & upgrade of communication equipment at various sewer pump stations to allow for the remote monitoring of conditions
Location: Various Locations
Project Manager:
Todd Eising
Consultant: Tesco
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $95,000
3.

Title: Installation of Water System Sampling Stations
Description: Installation of sampling stations at various locations on the water distribution system to comply with new state drinking water regulations
Location: Various Locations

Project Manager: Vaughn Fleischbein
Designer: City Staff
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $25,000

4. Title: Water Service Replacement
Description: Replacement of deteriorated water services at various locations
Location: Various Locations
Project Manager: Todd Eising

Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000
5. Title: Water Meter Installation Project
Description: Installation of water meters throughout the City
Location: Various locations
Project Manager: Marcus Yasutake
Contractor:  Marques Pipeline
Start Date: November, 2008
Estimated Completion Date: February, 2010
Estimated Project Cost: $3,406,000
Percent Complete:  40%
6. Title: Nimbus Tank Rehabilitation Project
Description: Inlet piping modifications, internal and external paint recoat, and cathodic protection system
Location: Alabama Street and California Circle
Project Manager:
Marcus Yasutake
Contractor:  Crosno Construction, Inc.
Start Date: June, 2009
Estimated Completion Date: September, 2009
Estimated Project Cost: $630,000
Percent Complete:  0%

Title: Water Service Replacement
Description: Replacement of deteriorated water services at various locations
Location: Various Locations
Project Manager:
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000

Title: Water Service Replacement
Description: Replacement of deteriorated water services at various locations
Location: Various Locations
Project Manager:
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000

Water Service Replacement
Description: Replacement of deteriorated water services at various locations
Location: Various Locations
Project Manager:
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000

Title: Water Service Replacement
Description: Replacement of deteriorated water services at various locations
Location: Various Locations
Project Manager:
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000

Location: Various Locations
Project Manager:
Start Date: On-going
Estimated Completion Date: On-going
Estimated Project Cost: $250,000